Work Profile Report [11W29]
Fin Plan
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 2555/111-2/06-76(पा्र0 आ0)07/05टी0सी0 दि0 26-9-06
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
134.34
Resanction Cost :
134.34
Tentative Cost :
1.06
Saving
133.28
Exp. Upto Last Fy :
1.06
For CFY 2025-2026
Remaining :
133.28
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1.06
Work deferred
Sanction on : 18 years 11 months ago
26 Sep 2006
Physical Progress:
At start of FY 2025-2026 :
15 %
Up to Date :
15 %
Tentative Completion date on : 3 years 9 months ago
31 Oct 2021
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 133.28 has been recorded as expected cost of work reduced from 134.34 to 1.06132 .
कार्य का निरस्तीकरण प्रस्तावित हैं इसलिए माँग शून्य की गयी हैं।
-- as on 17-Jul-2025