Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.2 | 4.6 | 4.6 | 0 |
11W429 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 1249/।।। (2)/19-61 (एम0एल0ए0/2017 दिनांक 06.03.2019
TS Amount (lakhs) : 228.81 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
228.81
Resanction Cost :
228.81
Tentative Cost :
228.81
Exp. Upto Last Fy : 212.40
For CFY 2024-2025
Remaining : 16.41
Demand : 3.09
Allotment : 3.09
Exp in CFY : 0.00
Total Up to Date Exp : 212.40
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
06 Mar 2019
Tentative Completion date:
3 years 3 months ago
31 Mar 2021
Actual Completion Date:
3 years 4 months ago
01 Mar 2021
Remark
Bottelneck: no issue
कार्य रखरखाव में हैं। -- as on 05-Oct-2023
Physical Peramenters