Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.25 | 2.25 | 1.000 | 1.25 | 1.250 | 0.000 |
11W434 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 1230/।।। (2)/19-60 (एम0एल0ए0)/2017 दिनांक 06.03.2019
TS Amount (lakhs) : 105.87 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
105.87
Resanction Cost :
105.87
Tentative Cost :
105.87
Exp. Upto Last Fy : 83.62
For CFY 2024-2025
Remaining : 22.25
Demand : 22.25
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 83.62
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
5 years 4 months ago
06 Mar 2019
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। पी0सी0 का कार्य प्रगति पर है। -- as on 16-Dec-2023
Physical Peramenters