Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.25 | 2.25 | 1.000 | 1.25 | 1.250 | 0.000 |
11W434 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 1230/।।। (2)/19-60 (एम0एल0ए0)/2017 दिनांक 06.03.2019
TS Amount (lakhs) : 105.87 Lacs
Financial Detail
Sanction Cost : 105.87 Lacs
Resanction Cost : 105.87 Lacs
Exp. Upto Last Fy : 83.62 Lacs
For CFY 2024-2025
Remaining : 22.25 Lacs
Demand : 22.25 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 83.62 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
5 years 2 months ago
06 Mar 2019
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। पी0सी0 का कार्य प्रगति पर है। -- as on 16-Dec-2023
Physical Peramenters