Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
11W484 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 1271/।।।(2)/19-58 (एम0एल0ए0)/2017 टी0सी0 दिनांक 07.03.2019 एवं एस0पी0डी0 1832 आर0-16 आर0आई0डी0एफ0-26 आई0एस0सी0 दिनांक 11.09.2020
TS Amount (lakhs) : 235.61 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
235.61
Resanction Cost :
235.61
Tentative Cost :
235.61
Exp. Upto Last Fy : 228.24
For CFY 2024-2025
Remaining : 7.37
Demand : 7.36
Allotment : 7.36
Exp in CFY : 0.00
Total Up to Date Exp : 228.24
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
07 Mar 2019
Tentative Completion date:
4 months 4 weeks ago
18 Feb 2024
Actual Completion Date:
4 months 4 weeks ago
18 Feb 2024
Remark
Bottelneck: no issue
दायित्व शेष हैं,कार्य रखरखाव में हैं। -- as on 26-Apr-2024
Physical Peramenters