Work Profile Report [11W503]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 929/।।। (2)/21-61 (एम0एल0ए0)/2017 टी0सी0-2 दिनांक 30.03.2021
TS Amount (lakhs) : 29.72 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
29.72
Resanction Cost :
29.72
Tentative Cost :
29.72
Exp. Upto Last Fy :
27.68
For CFY 2025-2026
Remaining :
2.04
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
27.68
Work completed
Sanction on : 4 years 6 months ago
30 Mar 2021
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
100 %
Tentative Completion date on : 3 years 11 months ago
31 Oct 2021
Actual Completion Date : 3 years 2 months ago
27 Jul 2022
Physical Linear Components
Remark
कार्य माह 07/2022 मे पूर्ण, दायित्व शेष। -- as on 06-Dec-2022
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand