Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1.000 | 0 | 0.000 | 0.000 |
11W522 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 2395/।।। (2)/21-61 (एम0एल0ए0)/2017 टी0सी0-।। दिनांक 04.08.2021
TS Amount (lakhs) : 60.33 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
60.33
Resanction Cost :
60.33
Tentative Cost :
60.33
Exp. Upto Last Fy : 57.78
For CFY 2024-2025
Remaining : 2.55
Demand : 1.70
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 57.78
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
04 Aug 2021
Tentative Completion date:
1 year 2 weeks ago
30 Jun 2023
Actual Completion Date:
1 year 2 weeks ago
30 Jun 2023
Remark
Bottelneck: no issue
कार्य अनुरक्षण में हैं। -- as on 04-May-2024
Physical Peramenters