Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.9 | 0.9 | 0.800 | 0.1 | 0.100 | 0.000 |
11W529 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4041/III (2)/21-61 (MLA)/2017 Date 20.09.2021
TS Amount (lakhs) : 59.48 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
59.48
Resanction Cost :
59.48
Tentative Cost :
59.48
Exp. Upto Last Fy : 34.16
For CFY 2024-2025
Remaining : 25.32
Demand : 23.60
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 34.16
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
2 years 9 months ago
20 Sep 2021
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
राजस्व विभाग द्वारा डिमार्केशन कर दिया गया है। -- as on 14-Jul-2024
Physical Peramenters