Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.2 | 1.2 | 1.200 | 0 | 0.000 | 0.000 |
11W538 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4832/III (2) / 21-61 (MLA) 2017 TC Date 12.10.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
52.48
Resanction Cost :
52.48
Tentative Cost :
52.48
Exp. Upto Last Fy : 50.66
For CFY 2024-2025
Remaining : 1.82
Demand : 1.50
Allotment : 0.00
Exp in CFY : 0.27
Total Up to Date Exp : 50.93
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 9 months ago
12 Oct 2021
Tentative Completion date:
2 years 2 weeks ago
30 Jun 2022
Actual Completion Date:
2 years 2 weeks ago
30 Jun 2022
Remark
Bottelneck: no issue
कार्य माह 06/2022 में पूर्ण, दायित्व शेष। कार्य अनुरक्षण के अन्तर्गत है। -- as on 22-Apr-2024
Physical Peramenters