Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.6 | 0.6 | 0.600 | 0 | 0.000 | 0.000 |
11W543 :
Administrative Approval Detail : शासनादेश संख्या 6035/।।। (2)/21-61 (एम0एल0ए0)/2017 टी0सी0 दिनांक 15.12.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 26.11 Lacs
Resanction Cost : 26.11 Lacs
Exp. Upto Last Fy : 22.89 Lacs
For CFY 2024-2025
Remaining : 3.22 Lacs
Demand : 0.35 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 22.89 Lacs
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 5 months ago
15 Dec 2021
Tentative Completion date:
1 year 1 month ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य माह 03/2023 में पूर्ण। कार्य अनुरक्षण के अन्तर्गत है। -- as on 22-Apr-2024
Physical Peramenters