Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.6 | 0.6 | 0.600 | 0 | 0.000 | 0.000 |
11W548 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 6035/।।। (2)/21-61 (एम0एल0ए0)/2017 टी0सी0 दिनांक 15.12.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
26.27
Resanction Cost :
26.27
Tentative Cost :
26.27
Exp. Upto Last Fy : 19.14
For CFY 2024-2025
Remaining : 7.13
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 19.14
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 7 months ago
15 Dec 2021
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
1 year 6 months ago
21 Dec 2022
Remark
Bottelneck: no issue
कार्य माह 03/2023 में पूर्ण। कार्य अनुरक्षण के अन्तर्गत है। -- as on 22-Apr-2024
Physical Peramenters