Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.562 | 0.562 | 0.562 | 0 | 0.000 | 0.000 |
11W564 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन, लोक निर्माण अनुभाग-2 के ई-फाईल पत्रांक 51071 दिनांक 11.05.2023
TS Amount (lakhs) : 27.13 Lacs
Financial Detail
Sanction Cost : 27.13 Lacs
Resanction Cost : 27.13 Lacs
Exp. Upto Last Fy : 26.61 Lacs
For CFY 2024-2025
Remaining : 0.52 Lacs
Demand : 0.15 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 26.61 Lacs
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 100 %
Sanction on :
1 year 1 week ago
11 May 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य अनुरक्षण में हैं। -- as on 04-May-2024
Physical Peramenters