Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.11 | 6.11 | 1.370 | 4.74 | 4.740 | 4.740 |
11W569 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ` शासनादेश संख्या 615/।।। (2)/23-03(सामान्य) 2023 दिनांक 22.02.2023 एवं प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0 देहरादून के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0-नि0।।। दिनांक 16.05.2023
TS Amount (lakhs) : 90.15 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
90.15
Resanction Cost :
90.15
Tentative Cost :
90.15
Exp. Upto Last Fy : 45.95
For CFY 2024-2025
Remaining : 44.20
Demand : 44.20
Allotment : 44.20
Exp in CFY : 19.09
Total Up to Date Exp : 65.04
Work completed
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
2 months 1 week ago
10 May 2024
Actual Completion Date:
2 months 1 week ago
10 May 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 06-Jun-2024
Physical Peramenters