Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15 | 15 | 0.000 | 15 | 15.000 | 15.000 |
11W570 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : कार्यालय प्रमुख अभियन्ता एवं विभागाध्यक्ष, उत्तराखण्ड ला0नि0वि0 देहरादून के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0 नि0।।। दिनांक 16.05.2023
TS Amount (lakhs) : 469.26 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
469.26
Resanction Cost :
469.26
Tentative Cost :
469.26
Exp. Upto Last Fy : 66.98
For CFY 2024-2025
Remaining : 402.28
Demand : 402.28
Allotment : 135.80
Exp in CFY : 128.21
Total Up to Date Exp : 195.20
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 81 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
4 months 1 day from now
19 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी०सी० कार्य पूर्ण। दीवारों का कार्य गतिमान। -- as on 25-Jun-2024
Physical Peramenters