Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 1.500 | 1.500 |
11W573 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड लो0नि0 अनुभाग-2 के शासनादेश संख्या - ई0 फाईल संख्या- 51071 लोक निर्माण अनुभाग-2 दिनांक 12.09.2023
TS Amount (lakhs) : 33.68 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
33.68
Resanction Cost :
33.68
Tentative Cost :
33.68
Exp. Upto Last Fy : 21.72
For CFY 2024-2025
Remaining : 11.96
Demand : 20.42
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 21.72
Work completed
Physical Progress:
At start of FY 2024-2025 : 62 %
Up to Date : 100 %
Sanction on :
9 months 2 weeks ago
29 Sep 2023
Tentative Completion date:
1 month 2 weeks ago
27 May 2024
Actual Completion Date:
2 months 2 days ago
15 May 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 03-Jun-2024