Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 1.500 | 0.000 |
11W573 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड लो0नि0 अनुभाग-2 के शासनादेश संख्या - ई0 फाईल संख्या- 51071 लोक निर्माण अनुभाग-2 दिनांक 12.09.2023
TS Amount (lakhs) : 33.68 Lacs
Financial Detail
Sanction Cost : 33.68 Lacs
Resanction Cost : 33.68 Lacs
Exp. Upto Last Fy : 21.72 Lacs
For CFY 2024-2025
Remaining : 11.96 Lacs
Demand : 11.96 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 21.72 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 62 %
Up to Date : 65 %
Sanction on :
7 months 2 weeks ago
29 Sep 2023
Tentative Completion date:
1 week 21 hours from now
27 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी03 का कार्य पूर्ण। -- as on 04-May-2024
Physical Peramenters