Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 1.000 | 0.000 |
11W578 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-Letter no 51071 लोक निर्माण अनुभाग- 2 dated 12-09-2023
TS Amount (lakhs) : 50.3 Lacs
Financial Detail
Sanction Cost : 50.30 Lacs
Resanction Cost : 50.30 Lacs
Exp. Upto Last Fy : 35.40 Lacs
For CFY 2024-2025
Remaining : 14.90 Lacs
Demand : 13.48 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 35.40 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 40 %
Sanction on :
8 months 1 week ago
12 Sep 2023
Tentative Completion date:
5 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में। -- as on 15-Dec-2023
Physical Peramenters