Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1 | 0 |
11W582 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के पत्रांक ई-फाईल संख्या 51071 लोक निर्माण अनुभाग-2 दिनांक 12.10.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 0.80 Lacs
Resanction Cost : 0.80 Lacs
Exp. Upto Last Fy : 0.09 Lacs
For CFY 2024-2025
Remaining : 0.71 Lacs
Demand : 0.71 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.09 Lacs
Survey work done
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 40 %
Sanction on :
7 months 1 week ago
12 Oct 2023
Tentative Completion date:
7 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वे कार्य पूर्ण। डी0पी0आर0 गठन की कार्यवाही गतिमान हैं। -- as on 03-May-2024
Physical Peramenters