Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.05 | 3.05 | 0.000 | 3.05 | 3.050 | 0.000 |
11W586 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के पत्रांक ई-फाईल संख्या 58555 लोक निर्माण अनुभाग-2 दिनांक 12.10.2023
TS Amount (lakhs) : 44.14 Lacs
Financial Detail
Sanction Cost : 44.14 Lacs
Resanction Cost : 44.14 Lacs
Exp. Upto Last Fy : 10.23 Lacs
For CFY 2024-2025
Remaining : 33.91 Lacs
Demand : 33.91 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 10.23 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 65 %
Sanction on :
7 months 1 week ago
12 Oct 2023
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी03 का कार्य पूर्ण।शेष का कार्य प्रगति में हैं। -- as on 04-May-2024
Physical Peramenters