Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.05 | 3.05 | 0.000 | 3.05 | 3.050 | 3.050 |
11W586 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के पत्रांक ई-फाईल संख्या 58555 लोक निर्माण अनुभाग-2 दिनांक 12.10.2023
TS Amount (lakhs) : 44.14 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
44.14
Resanction Cost :
44.14
Tentative Cost :
44.14
Exp. Upto Last Fy : 10.23
For CFY 2024-2025
Remaining : 33.91
Demand : 33.91
Allotment : 25.00
Exp in CFY : 29.17
Total Up to Date Exp : 39.39
Work completed
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 100 %
Sanction on :
9 months 5 days ago
12 Oct 2023
Tentative Completion date:
1 month 2 weeks ago
31 May 2024
Actual Completion Date:
1 month 2 weeks ago
31 May 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 03-Jun-2024