Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 1.000 | 1.000 |
11W588 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के पत्रांक ई-फाईल संख्या 51071 लोक निर्माण अनुभाग-2 दिनांक 12.10.2023
TS Amount (lakhs) : 45.06 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
45.06
Resanction Cost :
45.06
Tentative Cost :
45.06
Exp. Upto Last Fy : 9.92
For CFY 2024-2025
Remaining : 35.14
Demand : 33.80
Allotment : 0.00
Exp in CFY : 0.55
Total Up to Date Exp : 10.46
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 100 %
Sanction on :
9 months 5 days ago
12 Oct 2023
Tentative Completion date:
1 month 2 weeks ago
31 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 03-Jun-2024
Physical Peramenters