Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.000 | 0.5 | 0.500 | 0.000 |
11W589 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के पत्रांक ई-फाईल संख्या 51071 लोक निर्माण अनुभाग-2 दिनांक 12.10.2023
TS Amount (lakhs) : 28.46 Lacs
Financial Detail
Sanction Cost : 28.46 Lacs
Resanction Cost : 28.46 Lacs
Exp. Upto Last Fy : 4.42 Lacs
For CFY 2024-2025
Remaining : 24.04 Lacs
Demand : 23.20 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 4.42 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 90 %
Sanction on :
7 months 1 week ago
12 Oct 2023
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इंटर , टॉप एवं पी ० सी ० का कार्य पूर्ण। -- as on 18-May-2024
Physical Peramenters