Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.525 | 0.525 | 0.000 | 0.525 | 0.530 | 0.000 |
11W590 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के पत्रांक ई-फाईल संख्या 51071 लोक निर्माण अनुभाग-2 दिनांक 12.10.2023
TS Amount (lakhs) : 37.44 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.44
Resanction Cost :
37.44
Tentative Cost :
37.44
Exp. Upto Last Fy : 15.38
For CFY 2024-2025
Remaining : 22.06
Demand : 21.00
Allotment : 0.21
Exp in CFY : 0.28
Total Up to Date Exp : 15.66
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
9 months 5 days ago
12 Oct 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी0 2 का कार्य पूर्ण। -- as on 14-Jul-2024
Physical Peramenters