Work Profile Report [11W592]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन के शासनादेश संख्या - ई0 फाईल संख्या- 160997/2023 51071 लोक निर्माण अनुभाग-2 दिनांक 12.10.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
192.21
Resanction Cost :
192.21
Tentative Cost :
192.21
Exp. Upto Last Fy :
84.78
For CFY 2024-2025
Remaining :
107.43
Demand :
107.43
Allotment :
90.00
Exp in CFY :
62.73
Total Up to Date Exp :
147.51
Construction Started
Sanction on : 1 year 1 month ago
12 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
96 %
Tentative Completion date on : 2 days 7 hours from now
26 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.100 किमी0 लम्बाई में बी0सी0 का कार्य पूर्ण। -- as on 07-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand