Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.1 | 3.1 | 0.000 | 3.1 | 3.100 | 0.000 |
11W592 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के शासनादेश संख्या - ई0 फाईल संख्या- 160997/2023 51071 लोक निर्माण अनुभाग-2 दिनांक 12.10.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 192.21 Lacs
Resanction Cost : 192.21 Lacs
Exp. Upto Last Fy : 84.78 Lacs
For CFY 2024-2025
Remaining : 107.43 Lacs
Demand : 107.43 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 84.78 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 30 %
Sanction on :
7 months 1 week ago
12 Oct 2023
Tentative Completion date:
6 months 6 days from now
26 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में हैं। -- as on 04-May-2024
Physical Peramenters