Work Profile Report [11W657]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश संख्या ई-फाईल संख्या 56165/61 लोक निर्माण अनुभाग-2 दिनांक 17.12.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
24.92
Resanction Cost :
24.92
Tentative Cost :
14.05
Saving
10.87
Exp. Upto Last Fy :
5.38
For CFY 2025-2026
Remaining :
19.54
Demand :
8.67
Allotment :
15.00
Exp in CFY :
8.14
Total Up to Date Exp :
13.52
Work completed
Sanction on : 11 months 4 weeks ago
17 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
11 %
Up to Date :
100 %
Tentative Completion date on : 8 months 3 days ago
12 Apr 2025
Actual Completion Date : 7 months 4 days ago
11 May 2025
Physical Linear Components
Remark
Overall Saving 10.87 has been recorded as expected cost of work reduced from 24.92 to 14.05 . -- as on 05-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: