Administrative Approval Detail : शासनादेश संख्या ई-फाईल संख्या 56165/61 लोक निर्माण अनुभाग-2 दिनांक 17.12.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
26.79
Resanction Cost :
26.79
Tentative Cost :
15.74
Saving
11.05
Exp. Upto Last Fy :
12.23
For CFY 2025-2026
Remaining :
14.56
Demand :
2.75
Allotment :
2.75
Exp in CFY :
2.75
Total Up to Date Exp :
14.98
In Maintenance After Completion
Sanction on : 11 months 4 weeks ago
17 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 7 months 2 weeks ago
26 Apr 2025
Actual Completion Date : 7 months 2 weeks ago
26 Apr 2025
Physical Linear Components
Remark
Overall Saving 11.05 has been recorded as expected cost of work reduced from 26.79 to 15.74 . -- as on 05-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: