Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 36 | 36 | 36 | 0 |
125W12 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5377/111(2)/13-13 (मु0मं0घो0)/2012 दि0 24 दिसम्बर 2013
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 77.64 Lacs
Resanction Cost : 77.64 Lacs
Exp. Upto Last Fy : 60.74 Lacs
For CFY 2024-2025
Remaining : 16.90 Lacs
Demand : 2.00 Lacs
Allotment : 2.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 60.74 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
10 years 4 months ago
24 Dec 2013
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। अधिकाश कास्तकारों को प्रतिकर भुगतान कर दिया गया है। शेष कास्तकारो का भुगतान की कार्यवाही गतिमान। -- as on 29-Apr-2024
Physical Peramenters