Work Profile Report [125W142]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : 4520/।।।(2)/15-08(मु0मं0घो0)/2015 दिनांक 19.06.2015।
TS Amount (lakhs) : 7.2 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
43.14
Resanction Cost :
43.14
Tentative Cost :
43.14
Exp. Upto Last Fy :
8.37
For CFY 2025-2026
Remaining :
34.77
Demand :
1.94
Allotment :
1.31
Exp in CFY :
1.31
Total Up to Date Exp :
9.68
Work deferred
Sanction on : 10 years 5 months ago
19 Jun 2015
Physical Progress:
At start of FY 2025-2026 :
30 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वर्तमान में मार्ग सिचाई खण्ड पी0एम0जी0एस0वाई0 श्रीनगर द्वारा अधिग्रहित कर लिया गया है। -- as on 28-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2025 PWD Uttarakhand