Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 2 | 2 | 0 |
125W156 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 286/लो0नि0वि0/2004-15(प्र0आ0)/2004 दि0 27.02.2004
TS Amount (lakhs) : 55.6 Lacs
Financial Detail
Sanction Cost : 55.60 Lacs
Resanction Cost : 55.60 Lacs
Exp. Upto Last Fy : 55.15 Lacs
For CFY 2024-2025
Remaining : 0.45 Lacs
Demand : 2.24 Lacs
Allotment : 2.24 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 55.15 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
20 years 3 months ago
01 Feb 2004
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 08-Nov-2023
Physical Peramenters