Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
125W175 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2066/।।।(2)17-39(एम0एल0ए0)/2017 दि0 04.09.2017
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
17.68
Resanction Cost :
17.68
Tentative Cost :
17.68
Exp. Upto Last Fy : 29.80
For CFY 2024-2025
Remaining : -12.12
Demand : 5.00
Allotment : 4.00
Exp in CFY : 31.62
Total Up to Date Exp : 61.42
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 10 months ago
04 Sep 2017
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। मुआवजा भुगतान की कार्यवाही गतिमान। -- as on 02-May-2024
Physical Peramenters