Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 6.47 | 6.47 | 0 |
125W18 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4073 (1)/111 (2)/13-08 (प्रा0आ0)/2013, दि0 26 जून 2013
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 39.93 Lacs
Resanction Cost : 39.93 Lacs
Exp. Upto Last Fy : 32.13 Lacs
For CFY 2024-2025
Remaining : 7.80 Lacs
Demand : 5.00 Lacs
Allotment : 5.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 32.13 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
10 years 10 months ago
26 Jun 2013
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
कार्य पूर्ण। अधिकांश कास्तकारों को प्रतिकर भुगतान कर दिया गया है। शेष अनुपस्थित कास्तकारों को भुगतान की कार्यवाही गतिमान। -- as on 09-Feb-2024
Physical Peramenters