Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 6.47 | 6.47 | 0 |
125W18 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4073 (1)/111 (2)/13-08 (प्रा0आ0)/2013, दि0 26 जून 2013
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
39.93
Resanction Cost :
39.93
Tentative Cost :
39.93
Exp. Upto Last Fy : 32.13
For CFY 2024-2025
Remaining : 7.80
Demand : 5.00
Allotment : 2.00
Exp in CFY : 1.05
Total Up to Date Exp : 33.18
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 years 3 weeks ago
26 Jun 2013
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
कार्य पूर्ण। अधिकांश कास्तकारों को प्रतिकर भुगतान कर दिया गया है। शेष अनुपस्थित कास्तकारों को भुगतान की कार्यवाही गतिमान। -- as on 09-Feb-2024
Physical Peramenters