Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 2.5 | 0 |
125W187 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 3274/।।।(2)/17-39ृ(एम.एल.ए)/2017 दिनांक 27.12.17
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 12.09 Lacs
Resanction Cost : 12.09 Lacs
Exp. Upto Last Fy : 1.50 Lacs
For CFY 2024-2025
Remaining : 10.59 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.50 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 4 months ago
27 Dec 2017
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। मुआवजा भुगतान की कार्यवाही गतिमान। -- as on 30-Apr-2024
Physical Peramenters