Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
125W251 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 607/।।।(2)/19-38(एम0एल0ए0)/2017 दिनांक 07.02.2019
TS Amount (lakhs) : 17.9 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
17.90
Resanction Cost :
17.90
Tentative Cost :
17.90
Exp. Upto Last Fy : 0.50
For CFY 2024-2025
Remaining : 17.40
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.50
Work completed
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
20 Feb 2019
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मुआवजा भुगतान वितरण की कार्यवाही गतिमान। -- as on 02-May-2024
Physical Peramenters