Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 2.5 | 0 |
125W261 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 299/।।।(2)/19-39(एम0एल0ए0)/2017 दिनांक 25 जनवरी 2019
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
11.84
Resanction Cost :
11.84
Tentative Cost :
11.84
Exp. Upto Last Fy : 3.54
For CFY 2024-2025
Remaining : 8.30
Demand : 2.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 3.54
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 5 months ago
25 Jan 2019
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मुआवजा भुगतान वितरण की कार्यवाही गतिमान। -- as on 08-Nov-2023
Physical Peramenters