Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 1.5 | 0 |
125W321 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 1286/।।।(2)/20-387(एम0एल0ए0)/2017टी0सी0 दि0 13.07.2020
TS Amount (lakhs) : 90.35 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
90.35
Resanction Cost :
90.35
Tentative Cost :
90.35
Exp. Upto Last Fy : 82.68
For CFY 2024-2025
Remaining : 7.67
Demand : 2.72
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 82.68
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 4 days ago
13 Jul 2020
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। मार्ग अनुरक्षण अवधि में है। -- as on 08-Nov-2023