Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.35 | 3.35 | 3.35 | 0 |
125W335 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1323/।।।(2)/19-38(एम0एल0ए0)/2017 दिनांक 08 मार्च 2019
TS Amount (lakhs) : 211.26 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
211.27
Resanction Cost :
224.35
Tentative Cost :
224.35
Exp. Upto Last Fy : 214.48
For CFY 2024-2025
Remaining : 9.87
Demand : 1.50
Allotment : 8.77
Exp in CFY : 0.00
Total Up to Date Exp : 214.48
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
08 Mar 2019
Tentative Completion date:
2 years 6 months ago
16 Jan 2022
Actual Completion Date:
1 year 7 months ago
01 Dec 2022
Remark
Bottelneck: no issue
कार्य पूर्ण। मार्ग अनुरक्षण अवधि में है। -- as on 08-Nov-2023
Physical Peramenters