Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.35 | 3.35 | 3.35 | 0 |
125W335 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1323/।।।(2)/19-38(एम0एल0ए0)/2017 दिनांक 08 मार्च 2019
TS Amount (lakhs) : 211.26 Lacs
Financial Detail
Sanction Cost : 211.27 Lacs
Resanction Cost : 224.35 Lacs
Exp. Upto Last Fy : 214.48 Lacs
For CFY 2024-2025
Remaining : 9.87 Lacs
Demand : 1.50 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 214.48 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 2 months ago
08 Mar 2019
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। मार्ग अनुरक्षण अवधि में है। -- as on 08-Nov-2023