Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.925 | 0.925 | 0.925 | 0 |
125W373 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 2384/।।।(2)/21-39(एम0एल0ए0)/2017टी0सी0-3 दिनांक 04.08.2021
TS Amount (lakhs) : 59.42 Lacs
Financial Detail
Sanction Cost : 59.42 Lacs
Resanction Cost : 59.42 Lacs
Exp. Upto Last Fy : 51.59 Lacs
For CFY 2024-2025
Remaining : 7.83 Lacs
Demand : 3.50 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 51.59 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 9 months ago
04 Aug 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। मार्ग अनुरक्षण अवधि में है। -- as on 08-Nov-2023
Physical Peramenters