Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.85 | 1.85 | 2.700 | -0.85 | 1.850 | 1.850 |
125W375 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 3579(1)/।।।(2)/21-39(एम0एल0ए0)/2017टी0सी0-3 दिनांक 10.09.2021
TS Amount (lakhs) : 117.59 Lacs
Financial Detail
Sanction Cost : 117.59 Lacs
Resanction Cost : 122.02 Lacs
Exp. Upto Last Fy : 59.99 Lacs
For CFY 2024-2025
Remaining : 62.03 Lacs
Demand : 50.00 Lacs
Allotment : 19.69 Lacs
Exp in CFY : 19.27 Lacs
Total Up to Date Exp : 79.26 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 90 %
Sanction on :
2 years 8 months ago
10 Sep 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य पूर्ण। दायित्व अवशेष। -- as on 16-May-2024
Physical Peramenters