Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.85 | 1.85 | 2.700 | -0.85 | 1.850 | 1.850 |
125W375 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 3579(1)/।।।(2)/21-39(एम0एल0ए0)/2017टी0सी0-3 दिनांक 10.09.2021
TS Amount (lakhs) : 117.59 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
117.59
Resanction Cost :
122.02
Tentative Cost :
117.59
Saving
4.43
Exp. Upto Last Fy : 59.99
For CFY 2024-2025
Remaining : 62.03
Demand : 50.00
Allotment : 60.73
Exp in CFY : 37.86
Total Up to Date Exp : 97.85
Work completed
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
10 Sep 2021
Tentative Completion date:
2 months 2 weeks ago
30 Apr 2024
Actual Completion Date:
2 months 2 weeks ago
30 Apr 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व अवशेष। -- as on 04-Jul-2024