Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.17 | 2.17 | 2.17 | 0 | ||
Jobs | 1 | 0 | 0 |
125W433 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 ई-पत्रावली संख्या 23725/1/23725/2022 दिनांक 03.08.2022।
TS Amount (lakhs) : 64.89 Lacs
Financial Detail
Sanction Cost : 64.89 Lacs
Resanction Cost : 64.89 Lacs
Exp. Upto Last Fy : 31.88 Lacs
For CFY 2024-2025
Remaining : 33.01 Lacs
Demand : 8.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 31.88 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
2 years 9 months ago
03 Aug 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान का कार्य प्रगति पर -- as on 20-Apr-2023
Physical Peramenters