Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 30 | 30 | 30 | 0 |
125W485 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लो0नि0वि0 उत्तराखण्ड देहरादून के पत्रांक 323/14याता0(क0)-उ0/2023 दिनांक 10.03.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
536.39
Resanction Cost :
536.39
Tentative Cost :
536.39
Exp. Upto Last Fy : 514.38
For CFY 2024-2025
Remaining : 22.01
Demand : 22.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 514.38
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 4 months ago
10 Mar 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व अवशेष। -- as on 14-Nov-2023
Physical Peramenters