Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8.25 | 8.25 | 16.500 | -8.25 | 8.250 | 8.250 |
125W487 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लो0नि0वि0 देहरादून के पत्रांक संख्या 895/07याता0-पी0एम0जी0एस0वाई0-नि0।।। दिनांक 16.05.2023
TS Amount (lakhs) : 125.11 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
125.11
Resanction Cost :
125.11
Tentative Cost :
125.11
Exp. Upto Last Fy : 74.73
For CFY 2024-2025
Remaining : 50.38
Demand : 50.38
Allotment : 1.20
Exp in CFY : 1.21
Total Up to Date Exp : 75.94
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
5 months 1 week ago
05 Feb 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व अवशेष। -- as on 26-Jun-2024
Physical Peramenters