Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.5 | 9.5 | 9.500 | 0 | 9.500 | 5.000 |
125W489 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लो0नि0वि0 देहरादून के पत्रांक संख्या 895ध्07याता0-पी0एम0जी0एस0वाई0-नि0।।। दिनांक 16.05.2023
TS Amount (lakhs) : 112.37 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
112.37
Resanction Cost :
112.37
Tentative Cost :
112.37
Exp. Upto Last Fy : 58.25
For CFY 2024-2025
Remaining : 54.12
Demand : 54.12
Allotment : 54.12
Exp in CFY : 31.89
Total Up to Date Exp : 90.14
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 90 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 months 19 hours from now
18 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 25-Jun-2024