Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 11.9 | 11.9 | 11.9 | 0 |
125W490 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लो0नि0वि0 देहरादून के पत्रांक संख्या 895ध्07याता0-पी0एम0जी0एस0वाई0-नि0।।। दिनांक 16.05.2023
TS Amount (lakhs) : 179.03 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
179.03
Resanction Cost :
179.03
Tentative Cost :
179.03
Exp. Upto Last Fy : 175.83
For CFY 2024-2025
Remaining : 3.20
Demand : 3.20
Allotment : 3.20
Exp in CFY : 0.00
Total Up to Date Exp : 175.83
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
8 months 3 weeks ago
25 Oct 2023
Actual Completion Date:
4 months 1 week ago
10 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व अवशेष। -- as on 02-May-2024