Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.4 | 1.4 | 1.900 | -0.5 | 0.900 | 0.000 |
125W494 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-Patrawali No. 41863
TS Amount (lakhs) : 52.31 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
52.31
Resanction Cost :
52.31
Tentative Cost :
52.31
Exp. Upto Last Fy : 17.92
For CFY 2024-2025
Remaining : 34.39
Demand : 22.62
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 17.92
Work completed
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 90 %
Sanction on :
1 year 4 weeks ago
19 Jun 2023
Tentative Completion date:
10 months 1 week from now
31 May 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण । दायित्व अवशेष। -- as on 07-Jun-2024