Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.87 | 4.87 | 4.87 | 0 |
125W496 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 38360/2023 ई पत्रावली संख्या 48456 दिनांक 14.07.2023
TS Amount (lakhs) : 78.74 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
78.74
Resanction Cost :
78.74
Tentative Cost :
78.74
Exp. Upto Last Fy : 75.71
For CFY 2024-2025
Remaining : 3.03
Demand : 3.03
Allotment : 0.22
Exp in CFY : 0.00
Total Up to Date Exp : 75.71
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
1 year 3 days ago
14 Jul 2023
Tentative Completion date:
8 months 2 weeks ago
31 Oct 2023
Actual Completion Date:
7 months 3 weeks ago
24 Nov 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व अवशेष। -- as on 30-Oct-2023
Physical Peramenters