Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.66 | 3.66 | 3.66 | 0 |
125W497 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 38360/2023 ई पत्रावली संख्या 48456 दिनांक 14.07.2023
TS Amount (lakhs) : 23.52 Lacs
Financial Detail
Sanction Cost : 23.52 Lacs
Resanction Cost : 23.52 Lacs
Exp. Upto Last Fy : 23.28 Lacs
For CFY 2024-2025
Remaining : 0.24 Lacs
Demand : 0.24 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 23.28 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
10 months 5 days ago
14 Jul 2023
Tentative Completion date:
6 days 19 hours from now
26 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 02-May-2024