Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.9 | 3.9 | 3.9 | 0 |
125W499 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 38360/2023 ई पत्रावली संख्या 48456 दिनांक 14.07.2023
TS Amount (lakhs) : 62.3 Lacs
Financial Detail
Sanction Cost : 62.30 Lacs
Resanction Cost : 62.30 Lacs
Exp. Upto Last Fy : 58.49 Lacs
For CFY 2024-2025
Remaining : 3.81 Lacs
Demand : 3.81 Lacs
Allotment : 3.81 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 58.49 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
10 months 5 days ago
14 Jul 2023
Tentative Completion date:
2 months 6 days from now
26 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व अवशेष। -- as on 27-Oct-2023