Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 303.45 | 303.45 | 0.000 | 303.45 | 0.000 | 0.000 |
125W502 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 2451/।।।(2)/23-01(प्रा0आ0)/2019 दिनांक 21.07.2023
TS Amount (lakhs) : 1639.4 Lacs
Financial Detail
Sanction Cost : 1,639.40 Lacs
Resanction Cost : 1,639.40 Lacs
Exp. Upto Last Fy : 450.87 Lacs
For CFY 2024-2025
Remaining : 1,188.53 Lacs
Demand : 1,188.53 Lacs
Allotment : 595.00 Lacs
Exp in CFY : 246.03 Lacs
Total Up to Date Exp : 696.90 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 70 %
Sanction on :
9 months 4 weeks ago
21 Jul 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 23-Mar-2024
Physical Peramenters