Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.18 | 4.18 | 4.180 | 0 | 4.180 | 0.000 |
125W505 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 45543/2023 ई पत्रावली संख्या 48456 दिनांक 31.07.2023
TS Amount (lakhs) : 67.45 Lacs
Financial Detail
Sanction Cost : 67.45 Lacs
Resanction Cost : 67.45 Lacs
Exp. Upto Last Fy : 29.81 Lacs
For CFY 2024-2025
Remaining : 37.64 Lacs
Demand : 37.60 Lacs
Allotment : 37.60 Lacs
Exp in CFY : 24.79 Lacs
Total Up to Date Exp : 54.60 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 80 %
Sanction on :
9 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 12-Feb-2024