Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.18 | 4.18 | 4.180 | 0 | 4.180 | 0.000 |
125W505 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 45543/2023 ई पत्रावली संख्या 48456 दिनांक 31.07.2023
TS Amount (lakhs) : 67.45 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
67.45
Resanction Cost :
67.45
Tentative Cost :
67.45
Exp. Upto Last Fy : 29.81
For CFY 2024-2025
Remaining : 37.64
Demand : 37.60
Allotment : 37.60
Exp in CFY : 24.79
Total Up to Date Exp : 54.60
Work completed
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
3 weeks 6 days ago
20 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व अवशेष। -- as on 26-Jun-2024
Physical Peramenters