Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 12 | 12.000 | 0 | 12.000 | 0.000 |
125W506 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 45543/2023 ई पत्रावली संख्या 48456 दिनांक 31.07.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 287.73 Lacs
Resanction Cost : 287.73 Lacs
Exp. Upto Last Fy : 29.38 Lacs
For CFY 2024-2025
Remaining : 258.35 Lacs
Demand : 258.35 Lacs
Allotment : 100.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 29.38 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 70 %
Sanction on :
9 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
निर्माण कार्य प्रगति पर। -- as on 12-Feb-2024