Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 12 | 12.000 | 0 | 12.000 | 0.000 |
125W506 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 45543/2023 ई पत्रावली संख्या 48456 दिनांक 31.07.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
287.73
Resanction Cost :
287.73
Tentative Cost :
287.73
Exp. Upto Last Fy : 29.38
For CFY 2024-2025
Remaining : 258.35
Demand : 258.35
Allotment : 88.00
Exp in CFY : 82.96
Total Up to Date Exp : 112.34
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 70 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
5 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
6 मी0 एवं 01 मी0 पुलिया का कार्य पूर्ण। 10.300 में पी0सी0 का कार्य पूर्ण। सी0सी0 का कार्य प्रगति पर। -- as on 29-Jun-2024
Physical Peramenters