Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
125W507 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी गढवाल के पत्रांक सं0 306/09-प्रशा0अधि0 नजारत/2022-24 दिनांक 01.05.2023
TS Amount (lakhs) : 75.61 Lacs
Financial Detail
Sanction Cost : 75.61 Lacs
Resanction Cost : 75.61 Lacs
Exp. Upto Last Fy : 28.92 Lacs
For CFY 2024-2025
Remaining : 46.69 Lacs
Demand : 45.81 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 28.92 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
1 year 2 weeks ago
01 May 2023
Tentative Completion date:
9 months 21 hours from now
20 Feb 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 02-May-2024
Physical Peramenters