Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
125W508 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी गढवाल के पत्रांक सं0 306/09-प्रशा0अधि0 नजारत/2022-24 दिनांक 01.05.2023
TS Amount (lakhs) : 34.85 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
34.85
Resanction Cost :
34.85
Tentative Cost :
34.85
Exp. Upto Last Fy : 9.48
For CFY 2024-2025
Remaining : 25.37
Demand : 6.75
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 9.48
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
01 May 2023
Tentative Completion date:
7 months 1 week from now
25 Feb 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 02-May-2024