Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.775 | 0.775 | 1.075 | -0.3 | 0.475 | 0.000 |
125W512 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 158915/2023 ई पत्रावली संख्या . 36086 दिनांक 05.10.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 28.56 Lacs
Resanction Cost : 28.56 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 28.56 Lacs
Demand : 11.01 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
7 months 2 weeks ago
05 Oct 2023
Tentative Completion date:
1 year 2 months from now
31 Jul 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान का कार्य प्रगति पर। -- as on 08-Jan-2024
Physical Peramenters